Trench and excavation quantities
This is the point where a model stops being an analysis and starts being a price. A contractor does not buy “peak flow at outfall 1”. They buy cubic metres of dig, tonnes of granular bedding and lorry movements to tip, and all of it is already implied by the network.
BIM workflow & handover ▸ Trench & excavation quantities.
Method
Section titled “Method”Average end area, which is the method every civil quantity surveyor checks against. The trench cross-section is computed at each end of a pipe and averaged over the length between.
It is exact for a prism whose section varies linearly, and slightly conservative (over-measures) where the ground is convex, which is the right direction to be wrong in a tender.
What you set
Section titled “What you set”Support system decides the side slopes, and each option is cited:
- Shored, trench box or sheeting (vertical)
- Stable rock (vertical)
- Battered, UK practice (1:1)
- Battered, OSHA Type A (0.75:1), Type B (1:1) or Type C (1.5:1) soil
Then the dimensional allowances: minimum trench width, working space each side, wall allowance each side, bedding below invert, surround above crown, and a bulking factor for disposal volume. A minimum cover threshold flags pipes running shallower than you allow.
Where the model is georeferenced, ground levels can be sampled from terrain instead, which fills those gaps with something defensible.
Output
Section titled “Output”Per-pipe quantities and totals: excavation volume, bedding, surround, backfill and disposal. Click a pipe to zoom to it on the map. Export CSV for the bill.
The 3D underground view has a Trench excavation overlay that draws the dig around each pipe and shows the total volume with the unpriced count beside it, which is a quicker sanity check than reading the table.
Requires a Pro plan.