Biofiltration BMPs

Settling structures capture particle-bound pollutants: TSS, particulate metals. They do almost nothing for dissolved pollutants - PFAS, dissolved metals, nitrate. Those need engineered adsorptive media: activated carbon or biochar, iron filings, or aluminium residuals.

The Add biofiltration BMP button, in the Biofiltration BMP section of the Controls tab, adds two things at once, because either on its own gives a misleading answer.

1. A bio-retention LID with throttled media, placed on the subcatchments you choose:

ParameterValueWhy
Media depth762 mm (30 in)A deep bed
Ksat25.4 mm/hr (1.0 in/hr)Cut deliberately, to buy contact time
Porosity0.42Typical engineered media
LiningLined, with an underdrainControls where the water goes

This is the hydrology and the residence time, and it documents the engineered media for the SWPPP.

2. A node treatment at the LID’s drain node, carrying the pollutant credit. Defaults: TSS 90 percent, dissolved metals 60 to 75 percent, Total PFAS 85 percent.

The consequence is worth understanding: the node treatment applies to all flow through that node, not only the water that passed through the media. Put it on an outfall, or on a node immediately downstream of the BMP, so it is not silently treating flow the BMP never saw.

A first-flush sizing readout suggests a media footprint, as a percentage of area, that captures the first-flush volume. Click use to apply it. As with any first-flush figure, it is a modelled output for your storm and your catchment, not a rule of thumb carried over from elsewhere.

Verified on the Watertown model, and reproduced on both engines: a biochar BMP cut the outfall PFAS peak from 4.4 to 0.34 µg/L. The equivalent settling-only treatment left it unchanged.