I&I prioritisation
Infiltration and inflow is the core spend under every US SSO consent decree, and the question is not how much I&I do we have - the treatment works already answered that - but where to spend first.
Model data ▸ I&I prioritisation (basins). Run the model first.
Basins, and why they are incremental
Section titled “Basins, and why they are incremental”The network is split at metering points: outfalls, and the junctions where it genuinely branches. Each basin covers the pipe and the flow belonging to it and to no basin nested inside it.
Two ways to measure the ingress
Section titled “Two ways to measure the ingress”Wet run less dry run is the primary method, and it is what a flow survey does. Press Run dry-weather too and the model re-runs with the rainfall switched off. The difference is the rainfall-derived ingress; groundwater is in both runs and cancels out.
It needs no [DWF] at all, which matters: an inflow-driven model has an empty [DWF] and
every other metric would be unavailable on it.
Groundwater infiltration is the dry run’s flow above the declared dry-weather flow. It is valid even in a combined system, because dry weather has no runoff for it to hide behind.
Flow above declared [DWF] is the single-run fallback. It measures total ingress and needs
the model to declare its sanitary flow honestly.
One quantity is chosen for the whole ranking, named at the bottom of the panel, and it follows
what the model declares - a model with [GROUNDWATER] ranks on groundwater. Ranking basins
on different quantities would put a rainfall figure beside a groundwater one and call the
bigger number worse.
Warm-up is discarded
Section titled “Warm-up is discarded”A SWMM run starts with empty pipes, so its opening hours are the system filling rather than conveying. Averaging across them pulls every mean below the flow the network actually carries - far enough, on a real model, to turn the infiltration negative.
The first 25% of each run is dropped before any mean is taken, and the panel says how many reporting periods that was. A flow survey discards its warm-up for the same reason.
The rate
Section titled “The rate”Normalised as gpd per inch-diameter per mile of sewer (US) or m³/day per mm-km (SI), because a basin leaking 40 L/s is not worse than one leaking 10 L/s if it holds four times the pipe. Per inch-mile they are identical, and sending crews to the big number wastes the programme.
A peaking factor is reported too, and survives when the split does not.
What it refuses to measure, and says so
Section titled “What it refuses to measure, and says so”- Subcatchments draining into a basin - runoff and rainfall-derived ingress arrive together and nothing in a single model can split them. The rate is withheld; the peaking factor is not.
- No sanitary baseline and only one run - it points you at the dry run instead.
- A declared
[DWF]that does not reconcile. Where most basins route less dry-weather flow than[DWF]declares inside them, the panel says so prominently. (Check the warm-up first: a filling period is the commonest innocent cause, and it is now discarded by default.) That is a finding about the model - flow declared at nodes where it is diverted, stored or lost to flooding before the meter - and it makes any rate built on that baseline unsafe. - Pipes with no usable diameter are counted as pipe but kept out of the inch-mile denominator, with the count reported, because that makes their basin’s rate read high.
It ranks; it does not spend
Section titled “It ranks; it does not spend”A rate says where to look. Confirming a basin needs rehabilitation is a flow-isolation and CCTV exercise on the ground. The screening threshold is editable, is quoted in the model’s own units (the 3,000 figure is the US-customary convention; an SI model sees its equivalent in m³/d per mm-km), and is a screen rather than a standard - agencies and consent decrees differ.