Temporary works and outage planning
Every repair, lining job and connection needs a length of sewer out of service, and the question that decides the method is always the same: what happens upstream while it is off, and how big a pump keeps that from reaching the street?
Open Operations & reports ▸ Temporary works & outage planning.
1. Choose what goes out of service
Section titled “1. Choose what goes out of service”Click Pick a run on the map and click the two ends of the length to isolate. That picks the whole run between those nodes, the same trace-between-nodes behaviour used elsewhere in the app, so a 400 m length of main is two clicks rather than forty. Pick pipes one by one is there for a scattered set.
The outage is applied as a topology change, not a deletion. Your model is untouched and the run is reversible.
2. See what the outage does
Section titled “2. See what the outage does”The tool runs the model twice, once as-is and once with the length isolated, and reports the difference:
- Newly flooded nodes, which flooded only because of the outage
- Made worse, nodes that already flooded and now flood more
- Extra to the surface, the additional volume reaching the street
3. Size the over-pump
Section titled “3. Size the over-pump”From the upstream volume that can no longer get away, the tool proposes an over-pump duty and a pumping period. Press Verify by simulation and it applies that duty as a withdrawal at the suction point and runs the model again. The verification is a simulation, not arithmetic on the first result.
If flooding remains, the panel says so and offers Raise the duty and re-verify, which raises the duty and repeats the loop.
4. The statement for the contractor
Section titled “4. The statement for the contractor”Temporary works statement produces a print-ready page written for the person doing the work rather than for a modeller: what is isolated, the duty and running hours, the suction and discharge points, what still floods and by how much, and every assumption the sizing rests on. It prints what the tool could not determine as prominently as what it could.
That last part matters on site. A duty quoted without its assumptions gets treated as a guarantee.
Phased work
Section titled “Phased work”Where the job runs in stages, add phases with their own isolations and time windows. The programme summary reports the worst phase and sizes the duty for it, since the pump you hire has to cover the hardest stage, not the average one. Overlapping windows are flagged, because two phases live at once is a different network from either alone.
Temporary works requires a Pro plan.